RERA & buyer rights

Tracking Construction Progress via RERA Quarterly Updates

The builder's sales team says construction is on track — the RERA portal's quarterly filings are where you can actually check for yourself.

DrawMagic Team22 Aug 202612 min read
#rera-quarterly-updates#qpr-rera#track-construction#buyer-rights#first-time-buyer

You call the sales office to ask how construction is coming along on your under-construction flat, and the answer is almost always some version of "on track, sir, no issues." It's a reassuring sentence, and it's also completely unverifiable coming from the person whose job is to keep you calm and committed. If you've ever wanted a way to check construction progress that doesn't depend on trusting the sales team's tone of voice, there is one — and it's public, official, and updated every quarter by law.

It's called the Quarterly Progress Report, or QPR, and it's a filing every RERA-registered project is required to make on the state RERA portal. Most buyers never look at it, simply because they don't know it exists or don't know how to read it. This article walks through what a QPR actually contains, how to find yours, and how comparing two consecutive quarters can tell you more about your project's real status than a dozen phone calls to the sales office.

What QPRs Are and Why RERA Mandates Them

Section 11 of the Real Estate (Regulation and Development) Act, 2016 requires every registered promoter to keep the project's webpage on the RERA portal updated, including quarterly updates on the status of the project. This isn't an optional courtesy the builder extends to buyers — it's a statutory disclosure obligation tied to the project's RERA registration itself, meaning a promoter who fails to file can face consequences from the regulator, separate from whatever the buyer agreement says.

The logic behind this requirement is straightforward: RERA was built around the idea that buyers commit large sums of money years before possession, based almost entirely on promises and renderings. Quarterly disclosure was designed to replace some of that promise-based trust with periodic, dated, official fact — construction has reached this floor, this many units are booked, these approvals are in place — so that a buyer's understanding of the project doesn't depend entirely on what the promoter chooses to volunteer.

What a Quarterly Progress Report Typically Shows

A QPR generally includes several categories of information about the project, though exact formatting varies by state portal:

  • Status of construction — described stage-wise, such as foundation complete, a specific number of floors cast, or finishing work underway on particular blocks or towers.
  • Approvals and sanctions — updates on whether required statutory approvals (building plan sanctions, occupancy certificate status, and similar) have progressed since the last filing.
  • Units booked and sold — how many units in the project have been booked or sold as of the filing date, giving a sense of sales momentum.
  • Any changes to the project timeline or plan — amendments the promoter has filed, which themselves may be worth investigating further if a completion date has quietly shifted.

Because QPRs are filed every quarter and dated, they form a running, official history of the project — not just a single snapshot, but a series of snapshots you can line up against each other.

Step by Step: Finding and Reading Your Project's QPR

  1. Identify your project's RERA registration number. This is on your builder-buyer agreement, sale brochure, or can typically be found by searching the project name on your State RERA portal's project search.
  2. Navigate to your State RERA portal (MahaRERA, UP RERA, RERA Karnataka, and others each host their own portal with a project-search function).
  3. Search for your project using its registration number or name and open the project's public page.
  4. Locate the Quarterly Progress Report section, sometimes labeled "QPR," "Form 5," or "project status updates," depending on the state's portal design.
  5. Download or note the most recent QPR and, if available, the one from the previous quarter as well, for comparison.
  6. Compare construction-stage language, approval status, and booked-unit counts between the two filings to see whether real, dated progress occurred in the intervening three months.
  7. Save a dated copy of each QPR you review — screenshots or downloaded PDFs — so you build your own timeline independent of what the portal shows at any future point in time.

QPR Field, What It Tells You, and What Slippage Looks Like

QPR FieldWhat It Tells YouWhat Slippage Looks Like
Construction stagePhysical progress since last filing (e.g., floors cast, finishing stage)Same stage described in two or more consecutive quarters with no advancement
Approvals/sanctions statusWhether statutory clearances are progressing alongside constructionApprovals pending unchanged across multiple quarters, or a mismatch between claimed construction stage and approval status
Units booked/soldSales momentum and, indirectly, the project's cash-flow healthA sudden plateau in bookings alongside stalled construction can signal broader project stress
Revised timeline/plan changesWhether the promoter has formally altered the completion dateA quietly extended completion date buried in a filing amendment, not separately communicated to buyers

The most useful comparison is almost always the simplest one: pull two consecutive QPRs and check whether the construction-stage description actually changed. If it reads identically, or nearly identically, quarter over quarter, that's a concrete, dated signal worth following up on — far more concrete than a verbal assurance from the sales office.

State-Level Differences in QPR Format and Frequency

While Section 11's quarterly-update obligation applies nationwide, the format and depth of QPR filings vary by state portal:

  • MahaRERA publishes relatively detailed, structured QPRs, including construction-stage and financial disclosure elements, and has a well-used project-search interface.
  • UP RERA similarly publishes detailed project-status filings accessible through its portal's project search.
  • Other states follow the same underlying Section 11 requirement, but the depth of the online filing and how easily it's searchable can vary — in some cases, buyers may need to contact the regional RERA office directly if the online portal's project page is sparse.

Because of this variation, the first practical step for any buyer is simply to check what your specific State RERA portal actually displays for your project, rather than assuming every state's QPR looks the same.

Real-World Scenario: A Pune Buyer Compares Two Quarters

Consider a buyer who booked a 2BHK unit in an under-construction project in Pune's Hinjawadi corridor, with a builder-promised possession date roughly 18 months out. The sales team's periodic WhatsApp updates have consistently said "construction progressing well," without much specificity.

The buyer pulls up the project's page on the MahaRERA portal and finds two QPRs — one filed at the start of the quarter and one filed three months later. The earlier QPR describes the project as being at the "slab casting, floors 8-10" stage. The later QPR describes the same stage — "slab casting, floors 8-10" — with no advancement noted. Meanwhile, the units-booked figure has barely moved either. Taken together, these two dated, official filings tell the buyer something the sales team's verbal reassurances didn't: real physical progress appears to have stalled over that quarter, regardless of what conversations with the sales office suggested.

This doesn't necessarily mean something is fundamentally wrong with the project — construction can pause for legitimate reasons, including approval delays or monsoon-related site conditions. But it gives the buyer a concrete, dated basis to ask a specific, evidence-backed question rather than a vague one, and a documented starting point if the pattern continues into a third quarter.

Turning QPR Evidence into a Dated Record for Escalation

If a pattern of stalled progress continues across multiple quarters, the QPR filings themselves become useful evidence — not because they alone prove wrongdoing, but because they establish an official, dated timeline that's independent of the builder's verbal claims. This is exactly the kind of record a RERA complaint for delay (typically under Section 18, seeking compensation or a refund) would want to reference: a series of official filings showing the project didn't advance the way it was represented to be advancing.

Keeping this record organized as it accumulates — rather than trying to reconstruct it retroactively from memory when a delay becomes undeniable — is where DrawMagic's evolving Buyer Intelligence workspace fits in. It's designed to help buyers track a project's public QPR history over time in one place, an information-organization function that works with official public filings rather than any private or unverifiable claim. It does not certify a project's progress or make a determination about the builder — it simply keeps the dated public record accessible and organized for you.

Pro Tips for Monitoring QPRs Effectively

  1. Save every QPR you review, not just the most recent one. A single filing tells you a snapshot; a saved series tells you a trend.
  2. Compare construction-stage language word-for-word across quarters, not just skim for a general sense of progress — identical or near-identical descriptions across quarters are the clearest slippage signal.
  3. Cross-check the approvals-status field alongside construction stage — a project claiming advanced construction but with pending statutory approvals is worth a closer look.
  4. Set a quarterly reminder to check the QPR shortly after each filing window closes, so you're reviewing fresh filings rather than stale ones.
  5. Note the exact filing date of each QPR you save, since the dated nature of the record is what gives it evidentiary value later if needed.

Common Mistakes to Avoid

  1. Trusting sales-team verbal updates over the official QPR filing, when the two are inconsistent — the QPR is the dated, statutory record; the phone call is not.
  2. Checking the QPR only once, at booking time, and never again — the value of QPRs comes from comparing successive filings over the construction period.
  3. Not saving downloaded copies, leaving you unable to prove what an earlier QPR said if the portal is later updated or a filing is revised.
  4. Assuming a stalled QPR automatically means a RERA complaint is warranted — it's a signal to ask specific questions and keep tracking, not necessarily an immediate trigger for legal escalation.
  5. Overlooking state-specific portal quirks — assuming your project's QPR looks like a screenshot you saw for someone else's project in a different state.

An Honest Note on What This Tool Does and Doesn't Do

DrawMagic organizes official, publicly filed information — it does not generate, verify, or certify any project's construction progress, and it is not a substitute for physically visiting your site or consulting the RERA portal directly for the authoritative filing. Any conclusions drawn from comparing QPRs should be treated as a basis for asking informed questions, not as a final judgment about a specific builder or project. For legal remedies related to project delay, consult your State RERA portal's complaint process or a licensed advocate.

The voice-first companion at DrawMagic can help you log each quarter's QPR status as you review it, building your own running record without relying on memory. For how DrawMagic handles data you enter into the platform, see Responsible AI; for general guidance on organizing your project records, visit Help.

According to IBEF's Real Estate Industry in India report (February 2026), India's real estate sector is on track toward a US$1 trillion valuation by 2030 and currently contributes roughly 7.3% to GDP — a sector operating at this scale, with millions of buyers holding under-construction commitments at any given time, depends on exactly the kind of transparent, dated disclosure that Section 11's QPR requirement was designed to provide.

Key Takeaways

  • Section 11 of the RERA Act, 2016 requires every registered promoter to file Quarterly Progress Reports (QPRs) on the state RERA portal, disclosing construction stage, approvals, and booked units.
  • QPRs are an official, dated, public record — independent of whatever the sales team tells you verbally.
  • Find your project's QPR by searching its RERA registration number or name on your State RERA portal.
  • The most useful check is comparing two or more consecutive QPRs to see whether the construction-stage description has actually advanced.
  • Identical or near-identical construction-stage language across multiple quarters is the clearest sign of possible slippage.
  • QPR format and portal usability vary by state — MahaRERA and UP RERA offer relatively detailed, searchable filings.
  • Save every QPR you review, with its filing date, to build your own timeline independent of the live portal.
  • A pattern of stalled QPRs is a basis for informed questions or, if it continues, a documented starting point for a delay-related RERA complaint — not an automatic verdict on the builder.
  • DrawMagic helps organize your QPR-tracking history but does not certify or verify any project's actual progress.

Frequently Asked Questions

How often are QPRs supposed to be filed? Every quarter, per Section 11 of the RERA Act, 2016. If your project's portal page hasn't shown a new filing in significantly longer than three months, that itself may be worth flagging to your State RERA authority.

What if I can't find my project on the RERA portal at all? This can happen if the project isn't registered under RERA (which would itself be a serious concern) or if the search terms don't match the exact registered name. Try searching by the RERA registration number from your buyer agreement, and if the project genuinely doesn't appear, that's worth raising directly with your State RERA office.

Is a stalled QPR by itself enough to file a RERA complaint? Not necessarily on its own — but a documented pattern across multiple quarters, combined with other facts about delay, forms useful evidence for a Section 18 delay-compensation or refund complaint. Consulting a licensed advocate is advisable before filing.

Share this article

Enjoyed this read? Join our YouTube channel for continuous discovery.